CD-1 Decisions made by the Acquiring Authority
- 1.01 Report to the acquiring authority's Leader of the Council 15 November 2018
- 1.02 Report to the acquiring authority's Finance, Policy and Resources Committee 20 February 2020
- 1.03 Minutes of the acquiring authority's Finance, Policy and Resources Committee 20 February 2020
- 1.04 Report to the acquiring authority's Finance, Policy and Resources Committee 16 November 2020
- 1.05 Minutes of the acquiring authority's Finance, Policy and Resources Committee 16 November 2020
- 1.06 Report to the acquiring authority's Finance, Policy and Resources Committee 28 June 2021 (CPO report) (including additional document)
- 1.07 Report to the acquiring authority's Finance, Policy and Resources Committee 28 June 2021 (update on the project)
- 1.08 Minutes of the acquiring authority's Finance, Policy and Resources Committee 28 June 2021
- 1.09 Report to the acquiring authority's Finance, Policy and Resources Committee 20 September 2021 (including 3 appendices)
- 1.10 Minutes of the acquiring authority's Finance, Policy and Resources Committee 20 September 2021
- 1.11 Report to the acquiring authority’s Finance, Policy and Resources Committee 19 January 2023
- 1.12 Minutes the acquiring authority’s Finance, Policy and Resources Committee 19 January 2023
CD-2 Planning policy documents
- 2.01 National Planning Policy Framework (as of 23 September 2021)
- 2.02 London Plan 2021
- 2.03 London Plan Housing SPG March 2016
- 2.04 London Borough of Richmond upon Thames Local Plan (adopted in July 2018 and March 2020)
- 2.05 Twickenham Area Action Plan 2013
- 2.06 London Borough of Richmond upon Thames Local Economic Assessment (October 2010)
- 2.07 London Borough of Richmond upon Thames Housing and Homelessness Strategy 2021-2026
- 2.08 London Borough of Richmond upon Thames Affordable Housing Supplementary Planning Document (March 2014)
- 2.09 Richmond Local Plan Pre-Publication Regulation 18 Draft Site Allocation 18 (December 2021)
CD-3 Planning Application 21/2758/FUL Documents
- 3.01 RIBA Full Design Brief
- 3.02 Planning Statement
- 3.03 Design and Access Statement - Part 01
- 3.03 Design and Access Statement - Part 02
- 3.03 Design and Access Statement - Part 03
- 3.03 Design and Access Statement - Part 04
- 3.03 Design and Access Statement - Part 05
- 3.03 Design and Access Statement - Part 06
- 3.03 Design and Access Statement - Part 07
- 3.03 Design and Access Statement - Part 08
- 3.03 Design and Access Statement - Part 09
- 3.03 Design and Access Statement - Part 10
- 3.03 Design and Access Statement - Part 11
- 3.03 Design and Access Statement - Part 12
- 3.03 Design and Access Statement - Part 13
- 3.04 Delivery and Servicing Plan
- 3.05 Affordable Housing Statement
- 3.06 Impact on Neighbouring Properties Report - Part 1
- 3.06 Impact on Neighbouring Properties Report - Part 2
- 3.07 Internal Daylight, Sunlight and Overshadowing Report
- 3.08 Air Quality Assessment
- 3.09 Flood Risk Assessment and SuDS Report
- 3.10 Framework Estate Management Strategy
- 3.11 Heritage, Townscape & Visual Impact Assessment - Part 1
- 3.11 Heritage, Townscape & Visual Impact Assessment - Part 2
- 3.11 Heritage, Townscape & Visual Impact Assessment - Part 3
- 3.12 Landscape & Public Realm Strategy - Part 1 (updated October 2022 - see CD-4.07)
- 3.12 Landscape & Public Realm Strategy - Part 2 (updated October 2022 - see CD-4.07)
- 3.12 Landscape & Public Realm Strategy - Part 3 (updated October 2022 - see CD-4.07)
- 3.13 Statement of Community Involvement
- 3.14 Transport Assessment - Part 1 (updated October 2022 - see CD-4.08)
- 3.14 Transport Assessment - Part 2 (updated October 2022 - see CD-4.08)
- 3.14 Transport Assessment - Part 3 (updated October 2022 - see CD-4.08)
- 3.14 Transport Assessment - Part 4 (updated October 2022 - see CD-4.08)
- 3.14 Transport Assessment - Part 5 (updated October 2022 - see CD-4.08)
- 3.14 Transport Assessment - Part 6 (updated October 2022 - see CD-4.08)
- 3.15 Travel Plan
- 3.16.1 BREEAM Pre-Assessment by Method Consulting LLP - Office
- 3.16.2 BREEAM Pre-Assessment by Method Consulting LLP - Retail
- 3.17 Existing Site Elevations Old Lido and Café Sunshine TRS-HAL-ZZ-ZZ-DR-A-2351-C01
- 3.18 Existing Site Elevations – King Street TRS-HAL-ZZ-ZZ-DR-A-2350-C01
- 3.19 Existing Site Plan TRS-HAL-ZZ-00-DR-A-2010-C01
- 3.20 Existing Site Sections Water Lane and Embankment TRS-HAL-ZZ-ZZ-DR-A-2301-C02
- 3.21 Existing Site Sections Wharf Lane and Diamond Jubilee Gardens TRS-HAL-ZZ-ZZ-DR-A-2300-C02
- 3.22 Proposed Site Sections Water Lane and Embankment TRS-HAL-ZZ-ZZ-DR-A-2601-C02
- 3.23 Proposed Site Sections Wharf Lane and Diamond Jubilee Gardens TRS-HAL-ZZ-ZZ-DR-A-2600-C02
- 3.24 Water Lane Building Long Elevations TRS-HAL-02-ZZ-DR-A-2661-C01
- 3.25 Water Lane Building – First Floor GA Plan TRS-HAL-02-01-DR-A-2561-C02
- 3.26 Water Lane Building Short Elevations TRS-HAL-02-ZZ-DR-A-2660-C01
- 3.27 Proposed Site Sections Water Lane with overlay of existing TRS-HAL-02-ZZ-DR-A-2605-C01
- 3.28 Water Lane Building Typical Bay TRS-HAL-02-ZZ-DR-A-2695-C01
- 3.29 Wharf Lane Building Long Elevations TRS-HAL-01-ZZ-DR-A-2651-C01
- 3.30 Wharf Lane Building – Ground Floor GA Plan TRS-HAL-01-00-DR-A-2550-C02
- 3.31 Wharf Lane Building Typical Bays TRS-HAL-01-ZZ-DR-A-2690-C01
- 3.32 Wharf Lane Building Short Elevations TRS-HAL-01-ZZ-DR-A-2650-C01
- 3.33 Proposed Site Sections – Wharf Lane TRS-HAL-01-ZZ-DR-A-2604-C01
- 3.34 Wharf Lane Building Gastro Pub/Restaurant Typical Bay TRS-HAL-01-ZZ-DR-A-2691-C01
- 3.35 Proposed Ground Floor GA Plan TRS-HAL-ZZ-00-DR-A-2500-C01
- 3.36 General Arrangement Plan DWG. NO 6975_100
- 3.37 Planning Committee Report 24 November 2022
- 3.38 Addendum to Planning Committee Report 24 November 2022
- 3.39 Minutes of Planning Committee 24 November 2022
- 3.40 Planning Permission dated 21 December 2022
CD-4 Other Documents
- 4.01 Guidance on Compulsory purchase process and The Crichel Down Rules, July 2019
- 4.02A Proposed Modifications CPO Plan (March 2023)
- 4.02B Revised Open Space Plan (March 2023)
- 4.03A Map A Open Space – Existing Designated Open Space
- 4.03B Map B Open Space – Existing Functioning Open Space
- 4.03C Map C Open Space – Future Designated Open Space
- 4.03D Map D Open Space – Future Functioning Open Space
- 4.03E Map E Scheme Land
- 4.03F Map F Open Space - Order Land, the Lost Open Space, the Exchange Land and the Retained Open Space
- 4.03G Map G Flood Zone – Existing
- 4.03H Map H Flood Zone - Scheme
- 4.03I Map I – Existing Highway Plan
- 4.03J Map J – Future Highway Plan
- 4.03K Map K – Existing Trust Management Area
- 4.03L Map L – Proposed Trust Management Area
- 4.04 Avison Young Report March 2021
- 4.05 Social Additional Value Report
- 4.06 Stopping Up Order Plan (February 2023)
CD-4 Other Documents continued (submitted after 9 May 2023)
- 4.07 Public Realm Strategy October 2022 (Part 1)
- 4.07 Public Realm Strategy October 2022 (Part 2)
- 4.08A - Appendix A - Scoping Note and Pre-Application Engagement
- 4.08B - Appendix B - Cycle Quality Audit
- 4.08C - Appendix C - LBRuT CPZ Review
- 4.08D - Appendix D - Revised Vehicle Swept-Paths
- 4.08E - Appendix E - ATZ Photos
- 4.08F - Appendix F - MCC Analysis
- 4.08G - Appendix G - Revised Road Safety Audit Stage 1
- 4.08H - Appendix H - Revised RSA1 Designers Response
- 4.08 Transport Assessment October 2022 (Part 1)
- 4.08 Transport Assessment October 2022 (Part 2)
- 4.09A - Arboricultural Impact Assessment and Arboricultural Method Statement
- 4.09B - Arboricultural Survey